August 6, 2020
2020-08-06T12:00:00
Bathing Beach Parking Lot
31 Summer St.
Hingham, MA 02043
Route 3A Task Force - Walking Discussion
Thursday, August 6, 2020
1. Call to order
2. Introduce Consultants & Divide into two walking groups
3. Walk and discuss key sections of 3A/Summer/Rockland Street Project for
landscaping considerations (estimate 15 minutes at each location and 5 minutes
transition time)
a. 3A/Otis Hill Road
b. 3A/Bathing Beach to Town Pier
c. 3A/North/Water Street Intersections
d. Summer Street Rotary
e. Summer Street/Barnes Wharf to Martins Lane
f. Summer Street/Martins Lane/Rockland Street Intersection
g. Rockland Street & George Washington Blvd Intersection
4. Discussion of feedback compilation, upcoming milestones, next meeting date
5. Adjourn
Please Note: Following state guidelines for COVID19 precautions, participants are
required to wear masks and observe social distance guidelines.