The WRWS will be starting a water replacement project on Downer Ave in the area of the Foster School. Over the next several days, residents in the area of Downer Ave between Lincoln St and Otis St will see mobilization of equipment and materials in preparation for the water main replacement project. This work will include Downer Ave, Crow Point Ln and Planters Field Ln. Work will begin next week on the water main on Downer Ave. The work on Downer Aver will be completed by August 25, 2023 in time for the start of school Upon completion of this work the crews will move to Planters Field Ln and then to Crow Point Ln. All work is expected to be completed by the end of the year weather permitting.
If you have any questions regarding this work, please contact Russell E. Tierney, Managing Director / Superintendent at 781-804-2304 or tierneyr@hingham-ma.gov
Downer Ave Locus