News Flash

Public Safety Facility Project

Posted on: September 15, 2023

September 15, 2023 Public Safety Facility Project Update

Hauling Soil Offsite

The demolition of the original building’s concrete slab, foundation, and retaining walls are 90% complete. The underground water/steam piping and electrical conduits have been removed and...

The demolition of the original building’s concrete slab, foundation, and retaining walls are 90% complete. The underground water/steam piping and electrical conduits have been removed and the new underground water piping have been installed on Essington Drive and Shipyard Drive. The next big tasks are piling/hauling the abundance of extra soil offsite, grading, and beginning the foundation footings for the new Public Safety Facility.

Underground Piping

Piping and Conduits

Grading Site

Hauling Soil Offsite

Facebook Twitter Email