National Grid: Natural Gas Work in Hingham

National Grid Notice

A message from National Grid:


March 7, 2018

Re: Natural Gas Work in Hingham.   ( work order # 1196425 )

Dear City Officials,

National Grid is committed to safely and reliably delivering energy to our community. That’s why we are replacing the natural gas main at
298 to 578 Main ST.;
7 to 16 Merrymount RD.;
1 to 20 Marshall RD.;
1 to 30 Aberdeen RD.;
1 to 10 Playground RD.;

Courtesy letters to Towerbrook RD.; Wilder RD.; Fairview ST.; Linscott RD.; Colby RD,; Leonard ST.; Pleasant ST.; Downing ST.; Arnold RD.; Pond ST.; Common ST., Hingham, MA.

As part of this project, we will also replace the natural gas service piping that connects the main to the customer’s gas meters. Approximately 309 premises are within the construction limits.

Construction days and hours:   Please note: This work will take place at NIGHT
Sunday 7pm – Monday 5am
Monday 7pm – Tuesday 5am
Tuesday 7pm – Wednesday 5am
Wednesday 7pm – Thursday 5am
Thursday 7pm – Friday 5am
Friday 7pm – Saturday 5am

Construction is expected to begin on March 12, 2018 and anticipated to last to October 1, 2018 weather permitting. We will work hard to complete this project promptly and with minimal disruption to the community. Visit ngrid.com/mainline to view a YouTube video on this gas main replacement process.  A second video explaining the replacement of the service pipe to customer homes is available at ngrid.com/serviceline.


Additional Resource from National Grid: Everything you need to know about upgrading the natural gas main on your street.