Contractor: Dig It Construction, E. Dennis, MA, 508-432-1635
Work Schedule: 8:00 AM – 4:00 PM
During the week of January 25, 2021, our focus will be on the Bulow Place water main and anticipate completing the installation by Wednesday, January 27. The crew will also pressure test and disinfect the water main on Bulow Road from #17 to Fottler Road. Samples will be taken from the water main on Bulow Road and if passed we may start service installations on Bulow Road by the end of the week. Notifications regarding service interruptions will be in writing to residents.
During the week of February 1, 2021, our focus will be on service connections on Bulow Road and Bulow Place and notifications regarding service interruptions will be in writing to residents.
Last week we completed the main on Bulow Road and installed all new fire hydrants except one. The hydrant installed has been move to the end of the project. Clean up and temporary paving completed on Bulow Road trenches, and a section of the new water main pressure tested and disinfected.
Over the next week, we do not anticipate any interruptions in water service but due to the age of the existing water main and the accuracy of existing records, there may be situations in which we will periodically shut down the water main. We apologize for any inconvenience this may cause and appreciate your patience during this project.
Please check our website www.weirriverwater.com for periodic updates regarding scheduled shut downs / service interruptions. Please check your washer prior to doing laundry as these shut downs may cause discolored water.
Should you have any questions, please feel free to contact Weir River Water System at 781-804-2304 or tierneyr@hingham-ma.gov.