Air vapor barrier and brick face of exterior façade is fully underway, while the majority of the interior CMU walls and steel wall framing is near completion.
Air vapor barrier and brick face of exterior façade is fully underway, while the majority of the interior CMU walls and steel wall framing is near completion.
The rebar/post-tension cables/electric conduit/concrete placement of the garage beams/slab has been completed and now the northern half will begin. Electrical, Plumbing and Mechanical piping is currently underway on all floors. Most of the roof has been installed and inspected by the commissioning team. Windows frames are arriving onsite, and installation will begin in the coming days.