Project Updates

  1. September 15, 2023 Public Safety Facility Project Update

    The demolition of the original building’s concrete slab, foundation, and retaining walls are 90% complete. The underground water/steam piping and electrical conduits have been removed and... Read on...
  2. August 1, 2023 Public Safety Facility Project Update to Select Board

    Bob Garrity, Chair of the PSF Building Committee, and Matt Hennessy, Owner’s Project Manager for the Town, presented an update on the PSF project to the Select Board on August 1, 2023. Read on...
  3. July 28, 2023 Public Safety Facility Project Update

    Approximately 50% of the original large slab/foundation walls have been demolished... Read on...
View All News

Construction Management Plan (click to enlarge)

HPSF Construction Management Plan